I'm upgrading our vCenter environment from 5.5 U3b to 6.5 U2. You can't upgrade SRM from 5.8.1 to 6.5.1, but can upgrade to 6.1.2. Is it possible to do a multi step upgrade of SRM from 5.8.1 to 6.1.2 to 6.5.1? So I upgrade the protected site vCenter from 5.5 U3b to 6.5 U2, then upgrade the protected SRM from 5.8.1 to 6.1.2 to 6.5.1, then the recovery vCenter from 5.5 U3b to 6.5 U2, then the recovery SRM from 5.8.1 to 6.1.2 to 6.5.1. Would that be a feasible upgrade process for SRM or is that not supported. I can't tell from the documentation I've looked at.
↧